Watnall, Nottinghamshire
The site was located on a former railway cutting some 15 metres deep.
Piled foundations were adopted and the highways and drainage were reinforced/suspended utilising a geo membrane.
Significant methane emissions were detected and a gas membrane and venting were adopted.
Client - Westbury Homes Plc
Contractor - Westbury Construction
Contract Sum - £9.0m